Below is an update on the construction progress achieved in January 2026 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include pouring of concrete at Level One to cap the Garage underneath the Arrival Lobby, which completes the connection of Buildings A and B, the start of Level Six at the south end of Building B, and the continuation of utilities, fireplaces, drywall, insulation, and windows in the fully wrapped Building C.
Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams
Scroll down to view recent progress for the month of January in the sequential photos below:

Above: Looking from the top of Building B as crews wrap up the concrete pour at Level One underneath the Arrival Lobby. This level serves as the cap for the parking garage and completes the connection between Building A and Building B. January 28, 2026.

Above: Crews working on the complex rebar grid for Level One at the east end of Building A. In the photo above, workers are standing in the area that will become the Fitness Center. January 29, 2026.

Above: A close-up view of the rebar grid and columns. January 29, 2026.

Above: Crews working on the complex rebar grid for Level One at the east end of Building A. The Lobby Floor and Garage Connection is covered with tarps, and crews are pouring concrete to form the walls of the Garage Entry. January 29, 2026.

Above: Crews working on Level Six at the south end of Building B. At the north end, crews are working on framing and mechanical lines. January 29, 2026.

Above: Crews working on setting the complex rebar structure on Level Six at the south end of Building B. Once the rebar is in place, they can begin installing the PT cables. January 29, 2026.

Above: Crews have been working on window installation throughout units in Building C. The window frames are installed first, and the glass is placed into the frames afterward. January 29, 2026.

Above: A close-up view of the complicated roof structure to be used at the top-floor Penthouse units and Arrival Lobby. This unique design allows for a thick roof assembly with a thin, knife-edge above, to achieve the signature Olson Kundig look. Building C, January 29, 2026.