For the first time in Deer Valley’s history, the resort opened for Thanksgiving weekend, a week earlier than usual. They only had a few chairlifts and ski runs open, but the conditions were quite good, and the weather was sunny and beautiful. The season is off to a great start, with abundant natural snow coverage and continuous cold temperatures needed for snowmaking. The resort is working hard to open more terrain, and we should see many more chairlifts operating in the next couple of weeks.

Below is an update on construction progress for the end of November 2024 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include the start of horizontal shoring for Level Three at Building C, capping of the Basement Level and rebar assembly for the foundation slab of the P2 Level of Building B, and continuation of shear walls and columns for the first half of the Bowling Level at Building A.

Scroll down to view recent progress from the sequential photos below:

Above: Crews installing rebar for the vertical columns and shear walls at the Bowling Level of Building A. Once the walls at the perimeter are complete, they can backfill along the exterior, which will soon enable the temporary construction road to move to the west end of the site, wrapping around Building A. November 29, 2024.

The photo above is from our Construction Webcam 1. Click here to view the Live feed.

Above: A view of the construction site looking towards Building B, with Building C at the back right. We now have three cranes operating on the site. The tower crane in red is at the back, primarily for Building C, and two mobile cranes are operating at Buildings B and A. November 29, 2024.

The photo above is from our Construction Webcam 2. Click here to view the Live feed.

Above: Above is an elevated view from our Webcam 4. In the center is the P2 Garage Level (lower garage) of Building B. The completed columns and shear walls are visible in the front half. The back half is the completed rebar assembly that will form the west end of the P2 garage floor. November 29, 2024.

The photo above is from our Construction Webcam 4. Click here to view the Live feed.

Above: Our Webcam 5 shows the progress at Building C. The structural columns and shear walls are nearly complete on Level Two. Installation of the horizontal shoring has begun on Level Two, which will allow crews to start the construction of Level Three. Most of the shoring supports have been removed from the Garage Level and Level One, allowing for interior construction at those levels. November 29, 2024.

The photo above is from our Construction Webcam 5. Click here to view the Live feed.

Above: An overview of progress at Building B in the foreground and Building C in the background. November 29, 2024.

Above: Above is a detailed view of Building B. The lower Basement Level is now fully underground, and most of the columns and shear walls above are complete. The red tarps keep the complex rebar structure below free of snow in preparation for the massive concrete pour for the west end of the P2 Garage Level. November 30, 2024.

Above: Another view overlooking the P2 Garage Level of Building B. November 30, 2024.

Above: At Building C, most of the columns and shear walls are complete at Level Two. Crews have begun the installation of horizontal shoring to move up to the construction of Level Three. November 30, 2024.

Above: A detailed view from above the ski run, looking down at the horizontal shoring for Level Three of Building C. November 30, 2024.

Above: A detailed view from the south, looking across the entire Sommét Blanc site and the horizontal shoring for Level Three of Building C. Once the shoring and the decking are secured, crews will begin surveying the precise locations for structural features and plumbing penetrations for Level Three. November 30, 2024.