Below is an update on the construction progress for May 2025 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include the installation of steel framing for the roof on Level Eight at Building C, the installation of the temporary shoring deck for Level Two of Building A, and the installation of the temporary shoring deck for Level Two of Building B.

Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams

Scroll down to view recent progress for the month of May in the sequential photos below:

Above: Construction of vertical board-form concrete walls at Level One (amenity level) of Building B. The roof framing of Building C is visible in the background. May 27, 2025.

Above: Looking at the backside of Building B. Crews have completed most of the vertical columns and walls on Level One, and are working on the installation of the temporary shoring deck to begin Level Two. May 28, 2025.

Above: At Building A, the view shown above shows the Bowling Level and Garage Level below grade. Level One concrete was completed (Restaurant), and the temporary shoring deck is being installed to begin work on Level Two. May 27, 2025.

Above: The temporary shoring deck is being installed to begin work on Level Two. Work continues on the final section of the concrete shear wall tower for the elevator and stairwell. May 28, 2025.

Above: Framing has begun on Level Eight for the roof of Penthouse C801. May 28, 2025.

Above: Crews have completed most of the concrete elements at Level Eight (Penthouse C801) at Building C. Steel framing has begun for the roof of the Penthouse. May 28, 2025.

Above: Installation of the mechanical systems has begun for Building C. The image above shows the two-story entry lobby for the building. May 27, 2025.

Above: Installation of mechanical systems (electrical, plumbing, HVAC) has begun on the lower-level units in Building C. May 27, 2025.

Above: Installation of mechanical systems (electrical, plumbing, HVAC) has begun on the lower-level units in Building C. May 27, 2025.

Above: Installation of mechanical systems (electrical, plumbing, HVAC) has begun on the lower-level units in Building C. May 27, 2025.