Below is an update on the construction progress achieved in November 2025 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include the start of the shoring deck to cap the Garage Level at the east end of Building A, the pouring of concrete columns and walls at the Garage Level connecting Buildings A and B, the start of Level Four at the south end of Building B, and the continuation of utilities, fireplaces, and drywall in the fully wrapped Building C.

Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams

Scroll down to view recent progress for the month of August in the sequential photos below:

Above: Looking up at Building A. Framing is complete on levels two and three. They have begun wrapping the building, with utility lines being installed. November 30, 2025.

Above: Looking up at Building B and Building C in the background. Most of the framing is complete on the left side of Building B, and utility lines are being installed. On the right side, crews are starting on Level Four. Building C is fully wrapped, and most utilities are in place, with fireplaces, windows, and drywall being installed. November 30, 2025.

Above: The concrete walls and columns are mostly complete at the Garage Level, which connects Building A to Building B. Temporary shoring is being installed to begin the cap of the garage at Building A, which serves as the floor of the Fitness Center. The work above shows the waterproofing and insulation for the concrete walls. November 30, 2025.

Above: Another view of the Garage Level connecting Building A to Building B. Once this garage connection is complete, it will serve as the base for the Arrival Lobby. November 30, 2025.

Above: A view of Building A from the top of Building B. The concrete walls and columns are complete at the Garage Level, and crews are placing a temporary shoring deck to begin Level One. The Bowling Level, below grade and underneath the visible Garage Level, is no longer visible. November 30, 2025.

Above: Another view from above looking down at the Garage Level that connects Building A to Building B. November 30, 2025.

Above: The steel and concrete columns at Building B’s Level Three have been completed, and the crew is now placing a temporary shoring deck to begin Level Four. November 30, 2025.

Above: A view of concrete forms for the steel rebar columns at Level Three of Building B. November 30, 2025.

Above: Standing behind the Sommet Blanc site and looking down from the hillside. Building B on the left is up to Level Seven, the location of Penthouse B702. Building A on the right is up to Level Six, the location of Penthouse A602. Once the Garage Level connection between the two buildings is complete, it will serve as the base for the Arrival Lobby. November 30, 2025.