Below is an update on the construction progress for August 2025 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include waterproofing the base foundation at the east end of Building A, completion of PT cables at Level Five of the west end of Building A, concrete pour for the northern half of Level Five in Building B, and installation of steel-framed decks and exterior wallboard for Building C.
Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams
Scroll down to view recent progress for the month of August in the sequential photos below:

Above: Looking over the sheet pile retaining wall down to the crews working on waterproofing the base concrete foundation slab. Next steps will be the installation of the massive rebar grid assembly for the 3-foot-plus-thick concrete foundation at the eastern end of Building A. August 27, 2025.

Above: At Building C, most of the steel-framed decks have been installed on the southern side of the building. Additionally, the exterior framing is complete, and crews are installing the exterior wallboard in advance of window installation. August 29, 2025.

Above: Sun shade details are being completed at the rooftop of the Penthouse unit of Building C. Lower levels have been wrapped in plastic as crews are starting work on drywall. August 29, 2025.

Above: Building B will soon be wrapped on all four sides with temporary scaffolding, allowing crews to continue the installation of exterior wallboard, and soon, windows, insulation, and siding. August 29, 2025.

Above: Crews pouring concrete at Level Five of Building B. August 27, 2025.

Above: Looking down from Building C, to the installation of the temporary shoring deck for Level One of Building B. These exterior concrete walls are being waterproofed and insulated, and will soon be back-filled, allowing for more productive working space around the building. August 29, 2025.

Above: Looking down from Building C, to Building B and Building A. At Building B, you can see the crews have completed the concrete pour for Level Five. At Building A, they are wrapping up PT cable installation at Level Five and waterproofing the base concrete slab at the Bowling Level. Also, the elevator tower core has been completed at the south end of Building B, extending up to and beyond Level Seven. August 29, 2025.