Below is an update on the construction progress for September 2025 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include completion of the base foundation at the east end of Building A, concrete poured at Level Six of the west end of Building A, shoring deck installation for the northern half of Level Seven in Building B, and weather-proof wrapping for Building C.

Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams

Scroll down to view recent progress for the month of August in the sequential photos below:

Above: Looking down from Building B to the massive rebar grid assembly for the 3-foot-plus-thick concrete foundation at the eastern end of Building A. September 4, 2025.

Above: The massive base slab foundation has been poured for the eastern end of Building A. This creates the floor of the Bowling Level. Crews are working on the steel rebar assembly for the structural columns, exterior walls, and elevator core tower. The western end of Building A is at Level Six. September 17, 2025.

Above: Crews pouring concrete into the rebar grid assembly on the very complicated structure of Level One at the south end of Building B. This will be the location for the Ski Valet and Ski Lockers. September 19, 2025.

Above: The south end is now backfilled up to Level One. Three levels below grade are no longer visible. These include the P1 Garage Level, the P2 Garage Level, and the Basement Level. September 23, 2025.

Above: An overview of the site from Building C. September 23, 2025.

Above: Looking up at the buildings from the ski beach lawn at the base of the Ruby chairlift. Building A is at the front left of the photo, with the future restaurant on Level One behind the board-form concrete walls. September 23, 2025.

Above: Looking down to progress at Building B. At the northern end, crews are pouring concrete for the north elevator core, as well as setting up the temporary shoring deck to create the floor of Penthouse 702 at Level Seven. At the southern end, they are getting ready to create Level Two. Because the elevator core is already complete, these levels should rise quickly. September 30, 2025.

Above: Looking down at Building A. Level Six has been poured at the western end, and crews are working on structural columns and walls at the Bowling Level at the eastern end. September 30, 2025.

Above: Another view of the eastern end of Building A, now up to Level Five and Level Six. September 30, 2025.