Below is an update on the construction progress for July 2025 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include the start of Level Four at the western half of Building A, excavation of the eastern half of Building A and underneath the Lobby, construction of the northern half of Level Four in Building B, and construction of the southern half of the P1 Garage Level in Building B.

Curious to see daily progress, view our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams

Scroll down to view recent progress for the month of July in the sequential photos below:

Above: The temporary shoring deck for Level Four at the western end of Building A is complete. Crews will soon place plumbing sleeves, structural rebar, and PT cables. July 31, 2025.

Above: Excavation is nearly complete for Garage Level below the Lobby and for the eastern end of Building A. Underneath Building A, the foundation will be at the Bowling and Cafe Level. Then, the next level will be the garage that connects Building A to B. July 31, 2025.

Above: The northern half of Level Four at Building B is almost ready for concrete. Crews are finishing the installation of structural rebar and PT cables. Also seen above is the concrete wall of the south elevator core, which is nearly at full height. July 31, 2025.

Above: Another view of the workers placing structural rebar and PT cables for Level Four at the north end of Building B. The right side is unit B401, and the left side is unit B402. June 31, 2025.

Above: At the southern end of Building B, the lower P2 Garage Level is complete, and shown above is the structural rebar grid for the P1 Garage Level, nearly ready for concrete. July 31, 2025.

Above: An aerial view of Building A and Building B, with excavation nearly complete between them. July 31, 2025.