Below is an update on the construction progress achieved in June 2026 at Sommét Blanc in Empire Pass at Deer Valley® Resort. Milestones include nearing completion of the last remaining PT-concrete level in the project (Level Six in Building A), the construction of Level Seven penthouse roofs on Building B, the continuation of exterior wallboard, utility lines and mechanical systems in Buildings A and B, and the start of floors, ceilings, bathroom tile, and cabinets in Building C.
Curious to see daily progress? View our live construction cameras on YouTube: https://www.youtube.com/@SommetBlanc/streams
Scroll down to view recent progress for the month of June in the sequential photos below:

Above: Newly poured Level Five on the eastern half of Building A. June 5, 2026.

Above: Interior finishes have started in Building C. Here, workers are installing Poliform cabinets in the kitchen of Residence C201. June 30, 2026.

Above: Workers installing the PT-cables for Level Six of Building A in advance of what will be the final structural level concrete pour. June 30, 2026.

Above: A view of continuing work on the rooftop of Penthouses B703 and B702. Also shown here is work on the exterior wallboard installation and waterproofing. June 30, 2026.

Above: Workers setting up concrete forms for installation of the board-form concrete exterior on the elevator/stairwell towers of Building B. June 30, 2026.

Above: With scaffolding now wrapping Building B, crews are continuing work on waterproofing the exterior wallboard in advance of the upcoming window installation. June 30, 2026.